Here is the Roadwork Update for the Week of November 24th, 2025:
<blockquote></blockquote>
<p class="MsoNormal" align="center" style="text-align:center"><b
style="mso-bidi-font-weight:
normal"><u><span style="font-size:16.0pt;mso-bidi-font-size:12.0pt"><br>
</span></u></b></p>
<p class="MsoNormal" align="center" style="text-align:center"><b
style="mso-bidi-font-weight:
normal"><u><span style="font-size:16.0pt;mso-bidi-font-size:12.0pt">Week
of November
24<sup>th </sup>, 2025</span></u></b></p>
<p class="MsoNormal"><span
style="font-size:12.0pt;font-family:"Arial",sans-serif"> </span></p>
<p class="MsoNormal" style="text-align:justify"><span
style="font-size:12.0pt">The
following are the planned major work activities by Town of
Holden Departments.
The work schedule is subject to change based upon weather and
other factors.
Activities may be added or subtracted dependent on those
factors. Neighborhoods
directly impacted by the planned work will be separately
notified by the Town’s
Rave Alert and Smart 911 system, and updates may be found on the
Town’s
Facebook page. Questions regarding Department of Public Works
activities may be
directed to </span><a href="mailto:dpw_info@holdenma.gov"><span
style="font-size:12.0pt">dpw_info@holdenma.gov</span></a><span
style="font-size:12.0pt"> or (508) 210-5550. Questions regarding
Light
Department activities may be directed to (508) 210-5400. </span></p>
<p class="MsoNormal" style="text-align:justify"><span
style="font-size:12.0pt"> </span></p>
<p class="MsoNormal"><b style="mso-bidi-font-weight:normal"><u><span
style="font-size:12.0pt">Outside Agency and Private Work</span></u></b><span
style="font-size:12.0pt"></span></p>
<p class="MsoNormal"><span style="font-size:12.0pt"> </span></p>
<p class="MsoNormal"><u><span style="font-size:12.0pt">MassDOT
(Shrewsbury
Street-Doyle Road-Chapel Street-Holden Street Project)</span></u></p>
<p class="MsoNormal" style="margin-left:.5in;text-align:justify"><span
style="font-size:12.0pt"> </span></p>
<p class="MsoNormal"
style="margin-left:.5in;text-align:justify;text-indent:-.25in;
mso-list:l0 level1 lfo1;tab-stops:list 0in"><span
style="font-size:12.0pt;font-family:Symbol;mso-fareast-font-family:Symbol;
mso-bidi-font-family:Symbol"><span style="mso-list:Ignore">·<span
style="font:7.0pt "Times New Roman"">
</span></span></span><span style="font-size:12.0pt">The
contractor
has no planned road closures for the week of November 24<sup>th</sup>.
The
contractor will begin cleaning up for a winter work
shutdown, including some temporary
sidewalk paving being completed next week around Mountview
Middle School. Work
will resume in the spring to complete any remaining items left
on the project.</span></p>
<p class="MsoNormal" style="text-align:justify"><span
style="font-size:12.0pt"> </span></p>
<p class="MsoNormal" style="margin-left:.5in;text-align:justify"><span
style="font-size:12.0pt"> </span></p>
<p class="MsoNormal"><u><span style="font-size:12.0pt">Ripple Fiber
Broadband
Project</span></u></p>
<p class="MsoListParagraphCxSpFirst"><span style="font-size:12.0pt"> </span></p>
<ul>
<li class="MsoListParagraphCxSpMiddle"
style="text-align:justify;text-indent:-.25in;
mso-list:l1 level1 lfo2;tab-stops:list 0in"><span
style="font-size:12.0pt;font-family:Symbol;mso-fareast-font-family:Symbol;
mso-bidi-font-family:Symbol"><span style="mso-list:Ignore"><span
style="font:7.0pt "Times New Roman""> </span></span></span><span
style="font-size:12.0pt"> Crews will continue
subsurface conduit installation in the area of Highland Street
and Union Street,
as well as neighborhoods to the west of Highland Street to
Flagler Drive, and
to the East of Highland Street around Jamieson Road, Dorothy
Ave, and Fort
Sumter Drive.</span></li>
</ul>
<p class="MsoListParagraphCxSpMiddle" style="text-align:justify"><span
style="font-size:12.0pt"> </span></p>
<p class="MsoListParagraphCxSpLast" style="text-align:justify"><span
style="font-size:12.0pt"> </span></p>
<p class="MsoNormal" style="text-align:justify"><b
style="mso-bidi-font-weight:
normal"><u><span style="font-size:12.0pt">Department of Public Works</span></u></b><span
style="font-size:12.0pt"></span></p>
<p class="MsoNormal" style="text-align:justify"><span
style="font-size:12.0pt"> </span></p>
<p class="MsoNormal"
style="margin-left:.5in;text-align:justify;text-indent:-.25in;
mso-list:l0 level1 lfo1;tab-stops:list 0in"><span
style="font-size:12.0pt;font-family:Symbol;mso-fareast-font-family:Symbol;
mso-bidi-font-family:Symbol"><span style="mso-list:Ignore">·<span
style="font:7.0pt "Times New Roman"">
</span></span></span><span style="font-size:12.0pt">The
Highway
Division has no planned closures for the week of November 24<sup>th</sup>.</span></p>
<p class="MsoNormal"
style="margin-left:.5in;text-align:justify;text-indent:-.25in;
mso-list:l0 level1 lfo1;tab-stops:list 0in"><span
style="font-size:12.0pt;font-family:Symbol;mso-fareast-font-family:Symbol;
mso-bidi-font-family:Symbol"><span style="mso-list:Ignore">·<span
style="font:7.0pt "Times New Roman"">
</span></span></span><span style="font-size:12.0pt">Water
& Sewer
Division has no planned closures for the week of November 24<sup>th</sup>.<span
style="mso-spacerun:yes"> </span></span></p>
<p class="MsoNormal" style="text-align:justify"><span
style="font-size:12.0pt"> </span></p>
<p class="MsoNormal"><b style="mso-bidi-font-weight:normal"><u><span
style="font-size:12.0pt">Light Department</span></u></b><span
style="font-size:
12.0pt"></span></p>
<p class="MsoNormal" style="margin-left:.5in;text-indent:-.5in"><u><span
style="font-size:12.0pt"><span style="text-decoration:none"> </span></span></u></p>
<p class="MsoNormal"
style="margin-left:.5in;text-align:justify;text-indent:-.25in;
mso-list:l0 level1 lfo1;tab-stops:list 0in"><span
style="font-size:12.0pt;font-family:Symbol;mso-fareast-font-family:Symbol;
mso-bidi-font-family:Symbol"><span style="mso-list:Ignore">·<span
style="font:7.0pt "Times New Roman"">
</span></span></span><span style="font-size:12.0pt">Line
Division has
no planned closures for the week of November 24<sup>th</sup>.<span
style="mso-spacerun:yes"> </span></span></p>
<p class="MsoNormal"
style="margin-left:.5in;text-align:justify;text-indent:-.25in;
mso-list:l0 level1 lfo1;tab-stops:list 0in"><span
style="font-size:12.0pt;font-family:Symbol;mso-fareast-font-family:Symbol;
mso-bidi-font-family:Symbol"><span style="mso-list:Ignore">·<span
style="font:7.0pt "Times New Roman"">
</span></span></span><span style="font-size:12.0pt">Forestry
Division
has no planned closures for the week of November 24<sup>th</sup>.
<b style="mso-bidi-font-weight:normal"><u></u></b></span></p>
<p><br>
</p>
<pre class="moz-signature" cols="72">--
Joshua Lavigne
Civil Engineer
Town of Holden, MA</pre>